This is the Quick Start Guide for standard operation of a VSP-G1 unit. For first time operators, detailed information or troubleshooting, please refer to the User's Manual.
Standard Procedure
Pre spark procedure
- System is leak tight
- An appropriate filter has been installed (HEPA or better)
- Overpressure protection is in place and functioning
- Check that all electrode connections are ok
- Make all the necessary modifications and settings (confirm this is correct with Tobias)
Post spark procedure
- Stop particle production
- Flush system (9x of the system volume)
- Close off gas source
- Contain the (to be) exposed area
Retrieving the produced nanoparticles