== Standard Procedure ==
'''''Pre spark procedure'''''
* System is leak tight
* An appropriate filter has been installed (HEPA or better)
* Overpressure protection is in place and functioning
* Check that all electrode connections are ok
* Make all the necessary modifications and settings <span style="background:#FFFF00">(confirm this is correct with Tobias)</span>
 
'''''Post spark procedure'''''
* Stop particle production
* Flush system (9x of the system volume)
* Close off gas source
* Contain the (to be) exposed area
 
'''''Retrieving the produced nanoparticles'''''


== Standard Configurations ==
== Standard Configurations ==

Revision as of 13:26, 22 September 2016

This is the Quick Start Guide for standard operation of a G1 unit. For first time users, detailed information or trouble shooting, please refer to the User Manual.


Standard Procedure

Pre spark procedure

  • System is leak tight
  • An appropriate filter has been installed (HEPA or better)
  • Overpressure protection is in place and functioning
  • Check that all electrode connections are ok
  • Make all the necessary modifications and settings (confirm this is correct with Tobias)

Post spark procedure

  • Stop particle production
  • Flush system (9x of the system volume)
  • Close off gas source
  • Contain the (to be) exposed area

Retrieving the produced nanoparticles

Standard Configurations

Maintenance