This is the '''Quick Start Guide''' for standard operation of a VSParticle Generator One (VSP-G1) unit. For first time operators, detailed information or troubleshooting, please refer to the [https://docs.vsparticle.com/w/index.php/G1_User_Manual#Generator_One_.28G1.29_User_Manual'''''User Manual'''''].
This is the '''Quick Start Guide''' for standard operation of a VSParticle Generator One (VSP-G1) unit. For first time operators, detailed information or troubleshooting, please refer to the [https://docs.vsparticle.com/w/index.php/G1_User_Manual#Generator_One_.28G1.29_User_Manual'''''User Manual'''''].


== Printable version ==
<!-- == Printable version == -->
A themed and printable version of the quick start guide is available for download here:  
A themed and printable version of the quick start guide is available for download here:  
[[File:VSP-G1_Quick_Start_Guide.pdf|thumb|Quick Start Guide]]. A laminated copy of this version is included in the box in which the VSP-G1 is delivered.
[[File:VSP-G1_Quick_Start_Guide.pdf|thumb|Quick Start Guide]]. A laminated copy of this version is included in the box in which the VSP-G1 is delivered.


==Features of the VSP-G1==
== Ensure a safe system ==
* visual guide to the machine and its parts


==Standard Operation==
== Connect power & turn the system on ==  
''See the "Operating the system" <span style="background:#00FF00">[hyperlink]</span> chapter within the VSP-G1 User's Manual for a more detailed description of the standard procedure using a basic setup as a guide.''<br>


'''''Prepare the system for production'''''
== Perform electrode alignment procedure ==  
# Design/draw your flow diagram.
# Assemble the setup according to your specifications. (Ensure that the reactor is closed and mounted <span style="background:#00FF00">[hyperlink to Mounting the reactor in the Setup chapter of the User's Manual]</span> correctly!)
# Check the connections.
# Check the system for leak tightness and make adjustments if necessary. (See leak tightness protocol <span style="background:#00FF00">[hyperlink]</span>) <span style="background:#00FF00">[insert note about pressure safety in the right margin here]</span>


'''''Start nanoparticle production'''''
== Start gas flow ==
# Check for leaks if any changes were made to the system (see step 4 of ''Prepare the system for production'').
# Power up all systems.
# Ensure that the path to the exhaust is clear.
# Begin gas flow.
# Set target voltage and current using the dials on the VSP-G1.
# Press the start button to begin production.
<span style="background:#00FF00">[Insert stabilisation note in the right margin]</span>
'''''Remove your sample''''' <br> When the deposition system is full or when you’ve produced the desired amount of nanoparticles,
# Stop particle production.
# Flush the system <span style="background:#00FF00">[hyperlink]</span> (9 x τ).
# Stop the gas flow.
# Take out your sample following the procedure for your deposition system.


== Standard Configurations ==
== Set parameters and start sparking ==  


== Maintenance ==
== Stop sparking and shut down ==
 
* Leak tightness protocol
* Flushing the system
* Replacing the filter(s)
* Cleaning the reactor
* Replacing the electrodes
 
== Contact information ==
'''VSParticle'''<br>
Molengraafssingel, 10 <br>
2629JD Delft <br>
The Netherlands <br>
support@vsparticle.com <br>
www.vsparticle.com <br>
 
 
Last updated 15:19, 20 October 2016 (CEST)

Revision as of 10:57, 5 July 2017

This is the Quick Start Guide for standard operation of a VSParticle Generator One (VSP-G1) unit. For first time operators, detailed information or troubleshooting, please refer to the User Manual.

A themed and printable version of the quick start guide is available for download here: File:VSP-G1 Quick Start Guide.pdf. A laminated copy of this version is included in the box in which the VSP-G1 is delivered.

Ensure a safe system

Connect power & turn the system on

Perform electrode alignment procedure

Start gas flow

Set parameters and start sparking

Stop sparking and shut down